1. During the test, a uniformly distributed load equivalent to the difference between the rated mass and the tare weight of the container should be placed in the container and fully bolted.
2. The ground on which the offshore container falls should be a flat concrete floor or other hard surface. The ground may be covered with planks, which shall not exceed 50 mm in thickness.
3. Lift the marine container tilted so that the angle between the side beam and the end beam connected to the lowest angle on the bottom of the container and the ground is not less than 5°. On the bottom surface of the container, the height difference between the lowest corner point and the highest corner point should not be greater than 400 mm.
4. During testing, the corner with the worst stiffness should be selected as the lowest impacted corner.
5. The lowest corner point of the offshore container should be more than 50 mm away from the ground. The initial impact velocity of the offshore container touching the ground shall not be less than 1m/s.
6. After testing, the offshore container shall not show significant permanent deformation or damage. Small repairable open welds and deformations are allowed.
TLS will not proceed to the next production step until the marine container has passed the vertical impact test
2. The ground on which the offshore container falls should be a flat concrete floor or other hard surface. The ground may be covered with planks, which shall not exceed 50 mm in thickness.
3. Lift the marine container tilted so that the angle between the side beam and the end beam connected to the lowest angle on the bottom of the container and the ground is not less than 5°. On the bottom surface of the container, the height difference between the lowest corner point and the highest corner point should not be greater than 400 mm.
4. During testing, the corner with the worst stiffness should be selected as the lowest impacted corner.
5. The lowest corner point of the offshore container should be more than 50 mm away from the ground. The initial impact velocity of the offshore container touching the ground shall not be less than 1m/s.
6. After testing, the offshore container shall not show significant permanent deformation or damage. Small repairable open welds and deformations are allowed.
TLS will not proceed to the next production step until the marine container has passed the vertical impact test
The basic principle of the negative pressure system is to keep the pressure of the environment inside the container lower than that outside, so that the toxic gas or flammable gas in the container will not be directly discharged from the it, and the negative pressure system captures dangerous and infectious particles in the air, and it is removed with a blower and a set of filters.
The negative pressurized container provide by TLS typically has 2 fans, a small fan for normal mode and a large fan for emergency mode. When either fan is turned on, a negative pressure environment is formed inside. When only the small fan in the fume hood is turned on, the internal pressure is around -30~40Pa, and normal ventilation mode in the container; When the flammable gas/H2S low level alarm is triggered, the outdoor Ex-fan will automatically turn on, the internal pressure is around -130Pa and the container enter the emergency mood and it will automatically turn off when the gas concentration is lower than the set value. If the gas concentration does not decrease, the high-level alarm of flammable gas/H2S would sound, after the alarm lasts for 10 seconds, the power supply of the container will be cut off.
Negative pressure is a safe sealing solution which is widely used in lab containers, Mud Labs, etc.
The negative pressurized container provide by TLS typically has 2 fans, a small fan for normal mode and a large fan for emergency mode. When either fan is turned on, a negative pressure environment is formed inside. When only the small fan in the fume hood is turned on, the internal pressure is around -30~40Pa, and normal ventilation mode in the container; When the flammable gas/H2S low level alarm is triggered, the outdoor Ex-fan will automatically turn on, the internal pressure is around -130Pa and the container enter the emergency mood and it will automatically turn off when the gas concentration is lower than the set value. If the gas concentration does not decrease, the high-level alarm of flammable gas/H2S would sound, after the alarm lasts for 10 seconds, the power supply of the container will be cut off.
Negative pressure is a safe sealing solution which is widely used in lab containers, Mud Labs, etc.
The production process and requirements for TLS offshore container are as below:
1. Produce the container frame and weld the container.
All primary structural welds are required to be welded by a class-certified welder, and full penetration welding is required. For containers that have passed the third-party inspection, they are sprayed according to the paint process, and the paint package is suitable for the marine environment
2. Install the floor.
First, calcium silicate plates were laid on the lower deck, then fixed steel mesh was installed on the surface, then the upper deck dressings were laid on the steel mesh, and finally the deck dressings were laid on the floor. After construction is complete, the flatness of the floor is measured and accepted by professional quality inspectors.
3. Lay down insulation material.
Fix the nails in advance at the locations where the rock wool insulation needs to be laid in the container. When attaching the nails, reserve space to make sure that the nails are firmly attached according to the standard. Laying of rock wool ensures that the length of the overlapping surface is sufficient, and the joints are covered with fireproof tape.
4. Install water pipes, air pipes, and cable trays.
Pre-lay insulation. Reserve the supporting boom needed to install the pipe on the top plate of the container to ensure that the pipe is straight and firmly secured.
5. Install interior trim wall panels.
Install the fixing slot of the fixing plate first, and then install the inner panel in the fixing slot. Before installation, ensure that the surface of the wall panel and the ceiling is smooth and flat, and ensure that the splicing gap is neat and straight.
6. Install the furniture and appliances. The furniture in the container must be installed and secured according to the requirements and locations in the preliminary design drawings. The power connection of the relevant equipment shall be constructed in accordance with the regulations and must be inspected by qualified quality inspectors during this period.
7. Testing & Acceptance
TLS accepts client's on-site inspection, video inspection, graphic inspection, and other methods for acceptance. We will only ship the containers after they pass the acceptance.
1. Produce the container frame and weld the container.
All primary structural welds are required to be welded by a class-certified welder, and full penetration welding is required. For containers that have passed the third-party inspection, they are sprayed according to the paint process, and the paint package is suitable for the marine environment
2. Install the floor.
First, calcium silicate plates were laid on the lower deck, then fixed steel mesh was installed on the surface, then the upper deck dressings were laid on the steel mesh, and finally the deck dressings were laid on the floor. After construction is complete, the flatness of the floor is measured and accepted by professional quality inspectors.
3. Lay down insulation material.
Fix the nails in advance at the locations where the rock wool insulation needs to be laid in the container. When attaching the nails, reserve space to make sure that the nails are firmly attached according to the standard. Laying of rock wool ensures that the length of the overlapping surface is sufficient, and the joints are covered with fireproof tape.
4. Install water pipes, air pipes, and cable trays.
Pre-lay insulation. Reserve the supporting boom needed to install the pipe on the top plate of the container to ensure that the pipe is straight and firmly secured.
5. Install interior trim wall panels.
Install the fixing slot of the fixing plate first, and then install the inner panel in the fixing slot. Before installation, ensure that the surface of the wall panel and the ceiling is smooth and flat, and ensure that the splicing gap is neat and straight.
6. Install the furniture and appliances. The furniture in the container must be installed and secured according to the requirements and locations in the preliminary design drawings. The power connection of the relevant equipment shall be constructed in accordance with the regulations and must be inspected by qualified quality inspectors during this period.
7. Testing & Acceptance
TLS accepts client's on-site inspection, video inspection, graphic inspection, and other methods for acceptance. We will only ship the containers after they pass the acceptance.