• Fire and gas detection system send an alarm
  • All the personnel run to the muster point near the TR Complex
  • The TR F&G system run the emergency sequence operation, close the F&G dampers and lock the external doors
  • The diesel generators stop and the electric power is supplied by batteries
  • The HVAC system is switched from “fresh air” mode to “full recirculation” mode.
  • Is activated the compressed air pressurisation system and the BA system.
  • The air lock BA washing system is ready to start
  • The air lock doors are unlocked for the first mustering sequence
  • A predetermined number of personnel go inside the air lock (the TR doors are still closed)
  • Start the BA washing sequence inside the air lock (the air lock doors are now closed)
  • A toxic gas analyser verify the absence of gas (if the gas is revealed, start an additional washing sequence)
  • The TR rooms doors can be opened.
  • Start another mustering sequence (during the mustering, people outside the TR complex waiting for their turn are connected with the outdoor BA Cascade system)
  • People inside the TR rooms take their sit or their numbered position, waiting for the rescue vehicle or for the end of the alarm.
  • In case of TR evacuation (at the end of the 2 or 3 hours of emergency capacity of the TR), will start the disembarking sequence (through the air lock with only 1 washing sequence).